Originally posted by Kawac151:
I agree with you, very troublesome. I think TNM will also have the same situation once the PSDs are installed in a particular time.
North East Line PSD also open very slow , especially in CM mode.
Installation of half-height PSDs in above-ground MRT stations
Total of 54 sets for stns with 2 platforms, and 108 sets for stns with 4 platforms
Installed and Working:
1. PSR - 54 (LIVE as of 01/11/09)
2. YIS - 54 (LIVE as of 02/12/09)
3. JUR - 108 (LIVE as of 18/12/09)
Installing PSDs (3rd Stage)
01. Clementi (Eb - 23 + Wb - 23 = 46 --- 27/04/10)
02. Bukit Gombak (Nb - 5 --- 01/05/10)
Black-Yellow Panel (2nd Stage)
01.Lakeside
02.Chinese Garden
03.Bukit Batok
Red Markings (1st Stage)
01.Joo Koon
02.Pioneer
03.Boon Lay
04.Dover
05.Buona Vista
06.Commonwelth
07.Queenstown
08.Redhill
09. Kallang
10. Aljunied
11. Paya Lebar
12. Eunos
13. Kembangan
14. Bedok
15. Tanah Merah
16. Simei
17.Tampines
18. Choa Chu Kang
19. Yew Tee
20. Khatib
21. Yio Chu Kang
22. Ang Mo Kio
Updates:
14/04/10: Khatib added on 1st Stage
28/03/10: Clementi moved from 2nd Stage to 3rd Stage
21/03/10: Yew Tee added on 1st stage
15/03/10: Ang Mo Kio added on 1st stage
14/03/10: Yio Chu Kang added on 1st Stage
13/03/10: Kallang, Aljunied, Paya Lebar, Eunos, Bedok, Kembangan and Simei
added on 1st stage
04/03/10: Choa Chu Kang added on 1st stage
26/02/10: Tampines, Dover, Commonwelth, Queenstown, Buona Vista & Rehill
added on 1st stage
23/02/10: Pioneer & Tanah Merah added on 1st stage
12/02/10: Lakeside moved frm 1st stage to 2nd stage
09/02/10: Bukit Gombak moved from 1st stage to 2nd stage
06/02/10: Bukit Batok moved from 1st stage to 2nd stage
Joo Koon & Bukit Gombak added on 1st stage
31/01/10: Admiralty removed from 2nd stage
30/01/10: Chinese Garden moved from 1st stage to 2nd stage
Admiralty added on 2nd stage
---------------------------------------------------------------------------------------------------------------
Guessing Which Station In The East will Get HHPSD first?
(Do Not Include PSR) Up to 3 Guesses per person
(Closing Date : OVER )
Khairiano - Tanah Merah, Expo & Tampines
Bus and Train LoVuR - Kallang & Paya Lebar
LTnF1fan - Tampines, Bedok & Kallang
BiminiRosy - Tampines, Tanah Merah & Paya Lebar
smrt3099 - Expo, Bedok & Eunos
Scania96 - Bedok, Paya Lebar & Tampines
TIB770T - Eunos,Tanah Merah &Tampines
Samuel Lee - Tampines, Bedok & Paya Lebar
Chanzelun1996 - Eunos, Tampines & Kallang
Kawasaki C751B - Tanah Merah, Paya Lebar & Bedok
jayh272416 - Bedok, Tampines & Paya Lebar
SBS n SMRT - bedok, tanah merah & paya lebar
---------------------------------------------------------------------------------------------------------------
BUKIT GOMBAK has started PSDs installation already. Only about 3-4 sets of PSDs installed at the southbound platforms at the moment. Saw it on TRN 106 EWL crossover train.
Originally posted by tintinspartan:BUKIT GOMBAK has started PSDs installation already. Only about 3-4 sets of PSDs installed at the southbound platforms at the moment. Saw it on TRN 106 EWL crossover train.
ha, no one voting option D :)
Originally posted by Bus and Train LoVuR:Installation of half-height PSDs in above-ground MRT stations
Total of 54 sets for stns with 2 platforms, and 108 sets for stns with 4 platformsInstalled and Working:
1. PSR - 54 (LIVE as of 01/11/09)
2. YIS - 54 (LIVE as of 02/12/09)
3. JUR - 108 (LIVE as of 18/12/09)
Installing PSDs (3rd Stage)
01. Clementi (Eb - 15 + Wb - 17 = 32 --- 27/04/10)
Black-Yellow Panel (2nd Stage)
01.Lakeside
02.Chinese Garden
03.Bukit Batok
04.Bukit Gombak
Red Markings (1st Stage)
01.Joo Koon
02.Pioneer
03.Boon Lay
04.Dover
05.Buona Vista
06.Commonwelth
07.Queenstown
08.Redhill
09. Kallang
10. Aljunied
11. Paya Lebar
12. Eunos
13. Kembangan
14. Bedok
15. Tanah Merah
16. Simei
17.Tampines
18. Choa Chu Kang
19. Yew Tee
20. Khatib
21. Yio Chu Kang
22. Ang Mo Kio
Updates:
14/04/10: Khatib added on 1st Stage
28/03/10: Clementi moved from 2nd Stage to 3rd Stage
21/03/10: Yew Tee added on 1st stage
15/03/10: Ang Mo Kio added on 1st stage
14/03/10: Yio Chu Kang added on 1st Stage
13/03/10: Kallang, Aljunied, Paya Lebar, Eunos, Bedok, Kembangan and Simei
added on 1st stage
04/03/10: Choa Chu Kang added on 1st stage
26/02/10: Tampines, Dover, Commonwelth, Queenstown, Buona Vista & Rehill
added on 1st stage
23/02/10: Pioneer & Tanah Merah added on 1st stage
12/02/10: Lakeside moved frm 1st stage to 2nd stage
09/02/10: Bukit Gombak moved from 1st stage to 2nd stage
06/02/10: Bukit Batok moved from 1st stage to 2nd stage
Joo Koon & Bukit Gombak added on 1st stage
31/01/10: Admiralty removed from 2nd stage
30/01/10: Chinese Garden moved from 1st stage to 2nd stage
Admiralty added on 2nd stage
---------------------------------------------------------------------------------------------------------------
Guessing Which Station In The East will Get HHPSD first?
(Do Not Include PSR) Up to 3 Guesses per person
(Closing Date : OVER )
Khairiano - Tanah Merah, Expo & Tampines
Bus and Train LoVuR - Kallang & Paya Lebar
LTnF1fan - Tampines, Bedok & Kallang
BiminiRosy - Tampines, Tanah Merah & Paya Lebar
smrt3099 - Expo, Bedok & Eunos
Scania96 - Bedok, Paya Lebar & Tampines
TIB770T - Eunos,Tanah Merah &Tampines
Samuel Lee - Tampines, Bedok & Paya Lebar
Chanzelun1996 - Eunos, Tampines & Kallang
Kawasaki C751B - Tanah Merah, Paya Lebar & Bedok
jayh272416 - Bedok, Tampines & Paya Lebar
SBS n SMRT - bedok, tanah merah & paya lebar
---------------------------------------------------------------------------------------------------------------
Which station will get PSD delivered after CLE? (dateline: OVER!)
a) Chinese Garden
b) Lakeside
c) Bukit Batok
d) Bukit Gombak
People who answer: a) Chinese Garden - (6 votes)
azharj
Samuel Lee
LTnF1fan
Kawac151
Bus and Train LoVuR
SMRT/SBS Transit
People who answer: b) Lakeside- (4 vote)
yellowflip999
youyuan
SMB92U
Khairiano
People who answer: c) Bukit batok - (4 votes)
jcqh
TIB770T
c751bLoVuR
smrt3099
People who answer : d) Bukit Gombak (0 votes)
Oh lol! Where is the Northern stations?
hmmm I think bukit gombak stn not busy one
Originally posted by Samuel Lee:Oh lol! Where is the Northern stations?
Northern stations have not start work yet.
Clementi - 46 sets, 23 on each platform.
Update:
NS3 Bukit Gombak > 5 sets of NB platform
Originally posted by jcqh:Clementi - 46 sets, 23 on each platform.
wow..quite fast...
Originally posted by c751bLoVuR:Update:
NS3 Bukit Gombak > 5 sets of NB platform
oh man...
Originally posted by c751bLoVuR:Update:
NS3 Bukit Gombak > 5 sets of NB platform
So the winner of the "Which station will get PSD delivered after CLE?" is no one!
Originally posted by TIB770T:So the winner of the "Which station will get PSD delivered after CLE?" is no one!
Yup ,haha.
It is just too bad nobody got it right.![]()
Originally posted by SMRT/SBS Transit:It is just too bad nobody got it right.
And I don't think why first of May SMRT play us joke as April Fool???
dunno whether u guys got notice this or not
at jurong east station, only platform A & B PSDs have this sticker "platform A" & "platform B" pasted at the PSDs but not for platform C & D PSDs
why ar ? is it related to Jurong East Modification Project or they just dun want to put ?
I saw red markings at Kranji, Marsiling and Woodlands.
Originally posted by azharjj:dunno whether u guys got notice this or not
at jurong east station, only platform A & B PSDs have this sticker "platform A" & "platform B" pasted at the PSDs but not for platform C & D PSDs
why ar ? is it related to Jurong East Modification Project or they just dun want to put ?
Most likely that's because the middle platform does not really have a platform letter, that's why it's referred as "the middle platform".
Originally posted by slwsglz:PLATFORM screen doors to keep passengers from falling onto the train tracks - intentionally or otherwise - are being rolled out at more MRT stations.
Work is under way to get the doors up at the Clementi, Lakeside and Bukit Batok stations on the western end of the East-West line.
It will take between four and six months to install them, and they are expected to be ready in the second half of this year.
The LTA said it had decided to start with stations in the west, and then move to the east, before going up to those in the northern line.
Now PSD is currently installed at clementi which is correct as stated as above.but Bukit batok is next one but it become bukit gomak which psd is now installing. News from stratis time can mislead people which is reported in news few weeks back.
I am wondering if lakeside will be installed psd if it is true according to the news above.
Why nobody update the first post above this page?Should say 01/05/10:Bukit Gombak moved from 2nd stage to 3rd stage.EDIT:Correct me if I am wrong.
Originally posted by SMRT/SBS Transit:Why nobody update the first post above this page?Should say 01/05/10:Bukit Gombak moved from 2nd stage to 3rd stage.EDIT:Correct me if I am wrong.
I edited it already , maybe you saw it wrongly.
Huh? No news today for BGB?
Originally posted by c751bLoVuR:Huh? No news today for BGB?
Most likely no because PSD works will not commence on weekends. Anyway , I did not check.
Originally posted by slwsglz:Now PSD is currently installed at clementi which is correct as stated as above.but Bukit batok is next one but it become bukit gomak which psd is now installing. News from stratis time can mislead people which is reported in news few weeks back.
I am wondering if lakeside will be installed psd if it is true according to the news above.
ITS a YES to ST that Lakeside will be the next... cuz i saw 2 MEGA rolls of PSD cables
Deleted