NOTHING has happened in Lakeside since the 46th set of PSDs went up. Finish it before you start on another station, dammit.
I think they're thinking of installing them all at once and then operate them on the same day. Though I think they shouldn't think of doing ^. However, I don't really think they're doing ^ though.
Installation of half-height PSDs in above-ground MRT stations
Total of 27 sets per platform
Installed and Working:
1. PSR - 54 (LIVE as of 01/11/09)
2. YIS - 54 (LIVE as of 02/12/09)
3. JUR - 108 (LIVE as of 18/12/09)
Installing PSDs (3rd Stage)
01. Clementi (EB - 25 + WB - 25 = 50 --- 01/06/10)
02. Bukit Gombak (NB - 25 + SB 25 = 50 --- 04/06/10)
03. Lakeside (EB - 23 + WB - 23 = 46 --- 18/06/10)
04. Bukit Batok (NB - 25 + SB - 25 = 50 --- 25/07/10)
Black-Yellow Panel (2nd Stage)
01. Chinese Garden
02. Eunos
Red Markings (1st Stage)
01. Joo Koon
02. Pioneer
03. Boon Lay
04. Dover
05. Buona Vista
06. Commonwelth
07. Queenstown
08. Redhill
09. Kallang
10. Aljunied
11. Paya Lebar
12. Kembangan
13. Bedok
14. Tanah Merah
15. Simei
16. Tampines
17. Choa Chu Kang
18. Yew Tee
19. Kranji
20. Marsiling
21. Woodlands
22. Khatib
23. Yio Chu Kang
24. Ang Mo Kio
Updates:
10/07/10: Eunos moved to 1st stage to 2nd stage
24/06/10 : Bukit Batok moved from 2nd stage to 3rd stage
08/06/10: Lakeside moved from 2nd stage to 3rd stage
02/05/10: Kranji, Marsiling and Woodlands added on 1st stage
01/05/10: Bukit Gombak moved from 2nd stage to 3rd stage
14/04/10: Khatib added on 1st Stage
28/03/10: Clementi moved from 2nd Stage to 3rd Stage
21/03/10: Yew Tee added on 1st stage
15/03/10: Ang Mo Kio added on 1st stage
14/03/10: Yio Chu Kang added on 1st Stage
13/03/10: Kallang, Aljunied, Paya Lebar, Eunos, Bedok, Kembangan and Simei
added on 1st stage
04/03/10: Choa Chu Kang added on 1st stage
26/02/10: Tampines, Dover, Commonwelth, Queenstown, Buona Vista & Rehill
added on 1st stage
23/02/10: Pioneer & Tanah Merah added on 1st stage
12/02/10: Lakeside moved frm 1st stage to 2nd stage
09/02/10: Bukit Gombak moved from 1st stage to 2nd stage
06/02/10: Bukit Batok moved from 1st stage to 2nd stage
Joo Koon & Bukit Gombak added on 1st stage
31/01/10: Admiralty removed from 2nd stage
30/01/10: Chinese Garden moved from 1st stage to 2nd stage
Admiralty added on 2nd stage
---------------------------------------------------------------------------------------------------------------
Guessing Which Station In The East will Get HHPSD first?
(Do Not Include PSR) Up to 3 Guesses per person
(Closing Date : OVER )
Khairiano - Tanah Merah, Expo & Tampines
Bus and Train LoVuR - Kallang & Paya Lebar
LTnF1fan - Tampines, Bedok & Kallang
BiminiRosy - Tampines, Tanah Merah & Paya Lebar
smrt3099 - Expo, Bedok & Eunos
Scania96 - Bedok, Paya Lebar & Tampines
TIB770T - Eunos,Tanah Merah &Tampines
Samuel Lee - Tampines, Bedok & Paya Lebar
Chanzelun1996 - Eunos, Tampines & Kallang
Kawasaki C751B - Tanah Merah, Paya Lebar & Bedok
jayh272416 - Bedok, Tampines & Paya Lebar
SBS n SMRT - bedok, tanah merah & paya lebar
SBS8730A is temp replacing smrt3099 for user purposes is 099/100 is nowhere to be found
Currently PYL is progressing as Black/yellow panels marking instead, if you look carefully beyond the yellow line
EW25 Chinese Garden
Red Markings:
Black-Yellow Panel:
UPDATE : BBT NB platform has 13 sets of PSD. SB platform no change
Originally posted by c751bLoVuR:EW25 Chinese Garden
Red Markings:Black-Yellow Panel:
CNG have the panel for quite long already.
Updates of photos (PSD)
Lakeside

Bukit Batok


"BBT SB HW PSD OVERRIDE KEY SWITCH (NOT IN OPERATION)"
Bukit Gombak





Pioneer Platform A got Door number marking written with black marker on a masking tape.
Today

JEB-BBT 22
other side 23+1small door at end
Originally posted by jcqh:Today
LOL! It was blocked. Why the passengers still waiting this PSDs?? Anyway LOL!! Did the staff saw you? (female one)
Originally posted by c751bLoVuR:LOL! It was blocked. Why the passengers still waiting this PSDs?? Anyway LOL!! Did the staff saw you? (female one)
When the train arrives at the platform, the CSO would remove the cordon tape.
Once the train leaves, the cordon tape would be re-attached until the next train arrives.
@ jcqh - we was so close meeting :)
PSD spoilt + video



someone update this forum before it goes dead!
They're called threads or topics. ![]()
Lakeside's last PSDs are still happily lazing in the shade of the escalators.
Originally posted by mrtdude5:They're called threads or topics.
Lakeside's last PSDs are still happily lazing in the shade of the escalators.
then if construction cost USA,i can understand.but it dosent cost more than a few thousand to hire someone to get it up there,would it?
Originally posted by Dragonaxe:The whole Eunos have yellow-black markings except the 4 corners.
Hopefully JKN doesn't get them so soon.
That's the best place to take train ext pics.
well, lakeside still stuck 46th set...
Sorry for not updating on time : BBT both platform 25 PSD sets each.
Originally posted by Bus and Train LoVuR:Sorry for not updating on time : BBT both platform 25 PSD sets each.
updated.. see BBT reached 50 sets.. lakeside.. -.-"
Can i add JURNP (Jurong East New Platform) on 1st stage?