and also whether they deliver it ASAP...
Installation of half-height PSDs in above-ground MRT stations
Total of 27 sets per platform
Installed and Operational:
1. PSR - 54 (LIVE as of 01/11/09)
2. YIS - 54 (LIVE as of 02/12/09)
3. JUR - 108 (LIVE as of 18/12/09)
4. CLE - 54 (LIVE as of 16/08/10)
5. BGB - 54 (LIVE as of 16/08/10)
6. LKS - 54 (LIVE as of 31/08/10)
7. BBT - 54 (LIVE as of 31/08/10)
8. CNG - 54 (LIVE as of 01/10/10)
Installing PSDs (3rd Stage)
1. EUN - 46 (EB-23 WB-23)
2. PYL - 21 (EB - 16 WB - 5)
Black-Yellow Panel (2nd Stage)
01. Bedok
02. Aljunied
03. Kallang
04 Tanah Merah
05. Kembangan
Red Markings (1st Stage)
01. Joo Koon
02. Pioneer
03. Boon Lay
04. Dover
05. Buona Vista
06. Commonwealth
07. Queenstown
08. Redhill
09. Kallang
10. Simei
11. Tampines
12. Choa Chu Kang
13. Yew Tee
14. Kranji
15. Marsiling
16. Woodlands
17. Khatib
18. Yio Chu Kang
19. Ang Mo Kio
Updates:
31/10/10 Kembangan moved from 1st stage to 2nd stage
30/10/10: Tanah Merah moved from 1st stage to 2nd stage
28/10/10: Paya Lebar moved to Installation stage
15/10/10: Kallang moved from 1st stage to 2nd stage
05/10/10: Eunos is moved to Installation stage
01/10/10: Chinese Garden moved from 3rd stage to LIVE!
31/08/10: Lakeside and Bukit Batok moved from 3rd stage to LIVE!
16/08/10: Clementi and Bukit Gombak moved from 3rd Stage to LIVE!
14/08/10: Chinese Garden moved from 2nd stage to 3rd stage
03/08/10: Paya Lebar moved from 1st stage to 2nd stage
10/07/10: Eunos moved from 1st stage to 2nd stage
24/06/10 : Bukit Batok moved from 2nd stage to 3rd stage
08/06/10: Lakeside moved from 2nd stage to 3rd stage
02/05/10: Kranji, Marsiling and Woodlands added on 1st stage
01/05/10: Bukit Gombak moved from 2nd stage to 3rd stage
14/04/10: Khatib added on 1st Stage
28/03/10: Clementi moved from 2nd Stage to 3rd Stage
21/03/10: Yew Tee added on 1st stage
15/03/10: Ang Mo Kio added on 1st stage
14/03/10: Yio Chu Kang added on 1st Stage
13/03/10: Kallang, Aljunied, Paya Lebar, Eunos, Bedok, Kembangan and Simei
added on 1st stage
04/03/10: Choa Chu Kang added on 1st stage
26/02/10: Tampines, Dover, Commonwelth, Queenstown, Buona Vista & Rehill
added on 1st stage
23/02/10: Pioneer & Tanah Merah added on 1st stage
12/02/10: Lakeside moved frm 1st stage to 2nd stage
09/02/10: Bukit Gombak moved from 1st stage to 2nd stage
06/02/10: Bukit Batok moved from 1st stage to 2nd stage
Joo Koon & Bukit Gombak added on 1st stage
31/01/10: Admiralty removed from 2nd stage
30/01/10: Chinese Garden moved from 1st stage to 2nd stage
Admiralty added on 2nd stage
Eunos is spelt wrongly in the 05/10/10 update.
Eunos EB and WB have 23 sets of psds. While Kallang already have black-yellow panels.
I'm guessing TNM would be next to get yellow-black panels.
Paya Lebar Station Eastbound Platform has about 3-4 sets of doors at its eastern most end. Sorry couldn't confirm the number. (28102010)
Originally posted by ignoramuses:Paya Lebar Station Eastbound Platform has about 3-4 sets of doors at its eastern most end. Sorry couldn't confirm the number. (28102010)
Will double check again
Originally posted by smrt3099:Will double check again

Paya Lebar indeed have 5 sets of PSD as of today.
Okay. let's guess.. after Euons, Paya Lebar, Bedok, Aljunied, Kallang which Western Station will be next to install HHPSD?
01. Joo Koon
02. Pioneer
03. Boon Lay
04. Dover
05. Buona Vista
06. Commonwealth
07. Queenstown
08. Redhill
my guess would be either 03 or 05
03 as Boon Lay MRT station is always packed.
05 as to complement with the CCL opening.
Paya Lebar East Bound platform has 16 sets installed as of today.
[EDIT] Typo, missing a "1", makes a huge difference :P
Now PYL EB have 16 sets
Originally posted by i_luv_erky:Okay. let's guess.. after Euons, Paya Lebar, Bedok, Aljunied, Kallang which Western Station will be next to install HHPSD?
01. Joo Koon
02. Pioneer
03. Boon Lay
04. Dover
05. Buona Vista
06. Commonwealth
07. Queenstown
08. Redhill
my guess would be either 03 or 05
03 as Boon Lay MRT station is always packed.
05 as to complement with the CCL opening.
04. Dover
why? because dover have been received some of HHPSD =)
"Lu tanya wa siapa?? FFC the firefighter! PTPohhhh"
Tanah Merah Got a Few Black Yellow Panels Liao
Originally posted by EW26 Lakeside:04. Dover
why? because dover have been received some of HHPSD =)
"Lu tanya wa siapa?? FFC the firefighter! PTPohhhh"
got picture? =)
Originally posted by EW26 Lakeside:04. Dover
why? because dover have been received some of HHPSD =)
"Lu tanya wa siapa?? FFC the firefighter! PTPohhhh"
wah.. really? Dover received some HHPSD ? What about boon lay ?
Originally posted by ignoramuses:Paya Lebar Station Eastbound Platform has about 3-4 sets of doors at its eastern most end. Sorry couldn't confirm the number. (28102010)
WB got 5
Paya Lebar EB got 16 plus 1 "40% door" at HW
Paya Lebar WB got 5 at HW
Kembangan EB got some black-yellow panels (near TW)
Originally posted by Call4ljw:got picture? =)
monday i take the picture because i going for checkup at NUH
I think HHPSD will be installed at Bedok in the next few days because I saw they deliver it this afternoon.
Originally posted by Kawac151:Installation of half-height PSDs in above-ground MRT stations
Total of 27 sets per platform...
12. Choa Chu Kang
13. Yew Tee
14. Kranji
15. Marsiling
16. Woodlands
17. Khatib
18. Yio Chu Kang
19. Ang Mo Kio
...
How convenient. They skipped Sembawang completely.
Don't be surprised if it becomes the last station to get platform screen gates. SMRT has been neglecting Sembawang for a long time.
Originally posted by eX.A.K.R.:How convenient. They skipped Sembawang completely.
Don't be surprised if it becomes the last station to get platform screen gates. SMRT has been neglecting Sembawang for a long time.
Who say. Sembawang (Suicide in Vesak day 2010), Admiralty (Suicide in 2006 December) and Expo (No suicide heard of, but who knows who want to be the first one there) all dun have.
Originally posted by C751A 70049/70050:Who say. Sembawang (Suicide in Vesak day 2010), Admiralty (Suicide in 2006 December) and Expo (No suicide heard of, but who knows who want to be the first one there) all dun have.
Joo Koon and Pioneer is the newest. Before HHPSD was installed at Pasir Ris, JE, Yishun. I was thinking why not "they" install the HHPSD at Joo Koon and Pioneer first as that time was the opening of [JooKoon&Pioneer] and no HHPSD was installed yet. They should install it at there before opening the station
Originally posted by i_luv_erky:Joo Koon and Pioneer is the newest. Before HHPSD was installed at Pasir Ris, JE, Yishun. I was thinking why not "they" install the HHPSD at Joo Koon and Pioneer first as that time was the opening of [JooKoon&Pioneer] and no HHPSD was installed yet. They should install it at there before opening the station
What's done has already been done, well, I think they had thought of this, but maybe they had to test the station first in case anything crops up or something?
Originally posted by i_luv_erky:Joo Koon and Pioneer is the newest. Before HHPSD was installed at Pasir Ris, JE, Yishun. I was thinking why not "they" install the HHPSD at Joo Koon and Pioneer first as that time was the opening of [JooKoon&Pioneer] and no HHPSD was installed yet. They should install it at there before opening the station
They can't build, they only can prepare.(like JE jemp side)
moreover, JK and PSD are by different company i think.
Originally posted by SBS7338G:I think HHPSD will be installed at Bedok in the next few days because I saw they deliver it this afternoon.
Today there is some installed on the WB platform...
As for Paya Lebar.. only left with some HHPSD to be installed on the last few rows on the EB platform (near the escalator to the CCL)
Eunos HHPSD is STILL not in operation as of tdy