Originally posted by bus555:
Eunos HHPSD is STILL not in operation as of tdy
That's because they haven't install the TO doors yet
Originally posted by Kawac151:That's because they haven't install the TO doors yet
From what I can infer, maybe because EUN still dont have the HHPSD Summary Lamp. I hope they will not install the TO doors. By the way BDK WB HW has 3 sets of HHPSDs
Originally posted by SBS7338G:By the way BDK WB HW has 3 sets of HHPSDs
Yeah. Damn!

let the photo tell the story :(
Originally posted by youyuan:
let the photo tell the story :(
Hmm. Which station?
Originally posted by c751bLoVuR:Hmm. Which station?
I guess it's bedok.
Originally posted by c751bLoVuR:Hmm. Which station?
obviously is bedok...
Installation of half-height PSDs in above-ground MRT stations
Total of 27 sets per platform
Installed and Operational:
1. PSR - 54 (LIVE as of 01/11/09)
2. YIS - 54 (LIVE as of 02/12/09)
3. JUR - 108 (LIVE as of 18/12/09)
4. CLE - 54 (LIVE as of 16/08/10)
5. BGB - 54 (LIVE as of 16/08/10)
6. LKS - 54 (LIVE as of 31/08/10)
7. BBT - 54 (LIVE as of 31/08/10)
8. CNG - 54 (LIVE as of 01/10/10)
Installing PSDs (3rd Stage)
1. EUN - 48 (EB-24 WB-24)
2. PYL - 48 (EB - 24 WB - 24)
3. BDK - 24 (EB - 6 WB - 18)
4. ALJ - 17(EB - 17 WB - 0)
Black-Yellow Panel (2nd Stage)
01. Kallang
02. Tanah Merah
03. Kembangan
Red Markings (1st Stage)
01. Joo Koon
02. Pioneer
03. Boon Lay
04. Dover
05. Buona Vista
06. Commonwealth
07. Queenstown
08. Redhill
09. Kallang
10. Simei
11. Tampines
12. Choa Chu Kang
13. Yew Tee
14. Kranji
15. Marsiling
16. Woodlands
17. Khatib
18. Yio Chu Kang
19. Ang Mo Kio
Updates:
13/11/10 Aljunied moved to Installation stage
4/11/10 Bedok moved to Installation stage
31/10/10 Kembangan moved from 1st stage to 2nd stage
30/10/10: Tanah Merah moved from 1st stage to 2nd stage
28/10/10: Paya Lebar moved to Installation stage
15/10/10: Kallang moved from 1st stage to 2nd stage
05/10/10: Eunos is moved to Installation stage
01/10/10: Chinese Garden moved from 3rd stage to LIVE!
31/08/10: Lakeside and Bukit Batok moved from 3rd stage to LIVE!
16/08/10: Clementi and Bukit Gombak moved from 3rd Stage to LIVE!
14/08/10: Chinese Garden moved from 2nd stage to 3rd stage
03/08/10: Paya Lebar moved from 1st stage to 2nd stage
10/07/10: Eunos moved from 1st stage to 2nd stage
24/06/10 : Bukit Batok moved from 2nd stage to 3rd stage
08/06/10: Lakeside moved from 2nd stage to 3rd stage
02/05/10: Kranji, Marsiling and Woodlands added on 1st stage
01/05/10: Bukit Gombak moved from 2nd stage to 3rd stage
14/04/10: Khatib added on 1st Stage
28/03/10: Clementi moved from 2nd Stage to 3rd Stage
21/03/10: Yew Tee added on 1st stage
15/03/10: Ang Mo Kio added on 1st stage
14/03/10: Yio Chu Kang added on 1st Stage
13/03/10: Kallang, Aljunied, Paya Lebar, Eunos, Bedok, Kembangan and Simei
added on 1st stage
04/03/10: Choa Chu Kang added on 1st stage
26/02/10: Tampines, Dover, Commonwelth, Queenstown, Buona Vista & Rehill
added on 1st stage
23/02/10: Pioneer & Tanah Merah added on 1st stage
12/02/10: Lakeside moved frm 1st stage to 2nd stage
09/02/10: Bukit Gombak moved from 1st stage to 2nd stage
06/02/10: Bukit Batok moved from 1st stage to 2nd stage
Joo Koon & Bukit Gombak added on 1st stage
31/01/10: Admiralty removed from 2nd stage
30/01/10: Chinese Garden moved from 1st stage to 2nd stage
Admiralty added on 2nd stage
Originally posted by youyuan:obviously is bedok...
Why obviously? =.=
I only can tell that it is a station in the east as i stay in the north.
probably same for him
BDK WB HW - 6 sets
PYL both EB and WB have 24 sets.
hmm.. lets make a guess. when Jurong East next HHPSD will be installed ? I guess january or feburary
TNM Progress super slow... a few days liao still only a few black yellow panels, like never change at all
BDK WB have 9 sets
BDK WB HW - 14 sets
BDK
Aljunied have 6 sets of psds at EB platform
Originally posted by i_luv_erky:hmm.. lets make a guess. when Jurong East next HHPSD will be installed ? I guess january or feburary
It will be installed together with the new platform.
EW7 Eunos HHPSD will only be complete by this december. i saw the notice a few days ago.
Aljunied EB have 11 sets of psds.
Originally posted by Amir95express:EW7 Eunos HHPSD will only be complete by this december. i saw the notice a few days ago.
Wow they actually posted a notice?
Aljunied EB have 17 sets now.
KAL has a set of HHPSDs downstairs
Originally posted by Amir95express:EW7 Eunos HHPSD will only be complete by this december. i saw the notice a few days ago.
Where? Got Photo?
---