Total of 27 sets per platform
Installed and Operational:
1. PSR - 54 (LIVE as of 01/11/09)
2. YIS - 54 (LIVE as of 02/12/09)
3. JUR - 108 (LIVE as of 18/12/09)
4. CLE - 54 (LIVE as of 16/08/10)
5. BGB - 54 (LIVE as of 16/08/10)
6. LKS - 54 (LIVE as of 31/08/10)
7. BBT - 54 (LIVE as of 31/08/10)
8. CNG - 54 (LIVE as of 01/10/10)
Installing PSDs (3rd Stage)
1. EUN - 54 (EB-27 WB-27)
2. PYL - 48 (EB - 24 WB - 24)
3. BDK - 54 (EB - 27 WB - 27)
4. ALJ - 46(EB - 23 WB - 23)
5. JUR NEW PLATFORM -??(PE -? PF - ?)
Black-Yellow Panel (2nd Stage)
01. Kallang
02. Tanah Merah
03. Kembangan
04. Commomwealth
Red Markings (1st Stage)
01. Joo Koon
02. Pioneer
03. Boon Lay
04. Dover
05. Buona Vista
06. Queenstown
07. Redhill
08. Kallang
09. Simei
10. Tampines
11. Choa Chu Kang
12. Yew Tee
13. Kranji
14. Marsiling
15. Woodlands
16. Khatib
17. Yio Chu Kang
18. Ang Mo Kio
Updates:
08/12/10: Commomwealth is moved to Yellow/Panel Stage
13/11/10 Aljunied moved to Installation stage
4/11/10 Bedok moved to Installation stage
31/10/10 Kembangan moved from 1st stage to 2nd stage
30/10/10: Tanah Merah moved from 1st stage to 2nd stage
28/10/10: Paya Lebar moved to Installation stage
15/10/10: Kallang moved from 1st stage to 2nd stage
05/10/10: Eunos is moved to Installation stage
01/10/10: Chinese Garden moved from 3rd stage to LIVE!
31/08/10: Lakeside and Bukit Batok moved from 3rd stage to LIVE!
16/08/10: Clementi and Bukit Gombak moved from 3rd Stage to LIVE!
14/08/10: Chinese Garden moved from 2nd stage to 3rd stage
03/08/10: Paya Lebar moved from 1st stage to 2nd stage
10/07/10: Eunos moved from 1st stage to 2nd stage
24/06/10 : Bukit Batok moved from 2nd stage to 3rd stage
08/06/10: Lakeside moved from 2nd stage to 3rd stage
02/05/10: Kranji, Marsiling and Woodlands added on 1st stage
01/05/10: Bukit Gombak moved from 2nd stage to 3rd stage
14/04/10: Khatib added on 1st Stage
28/03/10: Clementi moved from 2nd Stage to 3rd Stage
21/03/10: Yew Tee added on 1st stage
15/03/10: Ang Mo Kio added on 1st stage
14/03/10: Yio Chu Kang added on 1st Stage
13/03/10: Kallang, Aljunied, Paya Lebar, Eunos, Bedok, Kembangan and Simei
added on 1st stage
04/03/10: Choa Chu Kang added on 1st stage
26/02/10: Tampines, Dover, Commonwelth, Queenstown, Buona Vista & Rehill
added on 1st stage
23/02/10: Pioneer & Tanah Merah added on 1st stage
12/02/10: Lakeside moved frm 1st stage to 2nd stage
09/02/10: Bukit Gombak moved from 1st stage to 2nd stage
06/02/10: Bukit Batok moved from 1st stage to 2nd stage
Joo Koon & Bukit Gombak added on 1st stage
31/01/10: Admiralty removed from 2nd stage
30/01/10: Chinese Garden moved from 1st stage to 2nd stage
Admiralty added on 2nd stage
BDK & ALJ
EB & WB : 23
How long as COM starts to have Black/Yellow Panels??
BDK
EB & WB: 27
Originally posted by smrt3099:How long as COM starts to have Black/Yellow Panels??
Febuary or March.. just my thought
Originally posted by EW26 Lakeside:Febuary or March.. just my thought
Well i just received am sms that COM got black/yellow panels already
Originally posted by smrt3099:Well i just received am sms that COM got black/yellow panels already
Confirmed by me + yy
Originally posted by smrt3099:Well i just received am sms that COM got black/yellow panels already
Commonwealth got Black/Yellow panals ?
Originally posted by i_luv_erky:Commonwealth got Black/Yellow panals ?
Yes. Good for Western Stn.
Eunos psds haven't operated yet...
Bedok HHPSDs Have Been Builded Finish (I Think) But Not Operatonal Yet
Yah! Tampines Is Going To Have HHPSDs Anyway All EWL Stations Will Have HHPSDs By Q4 2011
JEMP Platform is installing PSDs =P NOW
Info from SBS8945Y
I didnt expect new Jurong East platform starts to have new HHPSD, thats is expected during construction
Originally posted by SBS9231S:JEMP Platform is installing PSDs =P NOW
Info from SBS8945Y
Wow, that's unexpexting...=O
I didn't see Black/Yellow panals at commonwealth today
Originally posted by Kawac151:Wow, that's unexpexting...=O
I have to Jump Up and Down at JUR East Bound Platform Tail Wall to be able to see the PSDs -.- Looked like a freaking idiot. Maybe i shld grow taller =P
Originally posted by SBS9231S:I have to Jump Up and Down at JUR East Bound Platform Tail Wall to be able to see the PSDs -.- Looked like a freaking idiot. Maybe i shld grow taller =P
look from exterior view lor... =)
Originally posted by SBS9231S:I have to Jump Up and Down at JUR East Bound Platform Tail Wall to be able to see the PSDs -.- Looked like a freaking idiot. Maybe i shld grow taller =P
Jump more and you'll grow taller.
the "left most" side of the new platform at jurong east has all of the PSDs installed
not sure about the right most platform (aka the one on the left side of pasir ris bound train)
Originally posted by azharjj:the "left most" side of the new platform at jurong east has all of the PSDs installed
not sure about the right most platform (aka the one on the left side of pasir ris bound train)
No PSD Installed for That Platform Yet...
Originally posted by SBS9231S:I have to Jump Up and Down at JUR East Bound Platform Tail Wall to be able to see the PSDs -.- Looked like a freaking idiot. Maybe i shld grow taller =P
For me, i don't need to jump and down. I just crane my neck up can see abit liao.
Originally posted by Kawac151:For me, i don't need to jump and down. I just crane my neck up can see abit liao.
Oh don't show off... I know you're tall...
J/K
Originally posted by smrt3099:nstallation of half-height PSDs in above-ground MRT stations
Total of 27 sets per platformInstalled and Operational:
1. PSR - 54 (LIVE as of 01/11/09)
2. YIS - 54 (LIVE as of 02/12/09)
3. JUR - 108 (LIVE as of 18/12/09)
4. CLE - 54 (LIVE as of 16/08/10)
5. BGB - 54 (LIVE as of 16/08/10)
6. LKS - 54 (LIVE as of 31/08/10)
7. BBT - 54 (LIVE as of 31/08/10)
8. CNG - 54 (LIVE as of 01/10/10)
Installing PSDs (3rd Stage)
1. EUN - 54 (EB-27 WB-27)
2. PYL - 48 (EB - 24 WB - 24)
3. BDK - 54 (EB - 27 WB - 27)
4. ALJ - 46(EB - 23 WB - 23)
5. JUR NEW PLATFORM -??(PE -? PF - ?)Black-Yellow Panel (2nd Stage)
01. Kallang
02. Tanah Merah
03. Kembangan
04. Commomwealth
Red Markings (1st Stage)
01. Joo Koon
02. Pioneer
03. Boon Lay
04. Dover
05. Buona Vista
06. Queenstown
07. Redhill
08. Kallang
09. Simei
10. Tampines
11. Choa Chu Kang
12. Yew Tee
13. Kranji
14. Marsiling
15. Woodlands
16. Khatib
17. Yio Chu Kang
18. Ang Mo Kio
Updates:
08/12/10: Commomwealth is moved to Yellow/Panel Stage13/11/10 Aljunied moved to Installation stage
4/11/10 Bedok moved to Installation stage
31/10/10 Kembangan moved from 1st stage to 2nd stage
30/10/10: Tanah Merah moved from 1st stage to 2nd stage
28/10/10: Paya Lebar moved to Installation stage
15/10/10: Kallang moved from 1st stage to 2nd stage
05/10/10: Eunos is moved to Installation stage
01/10/10: Chinese Garden moved from 3rd stage to LIVE!
31/08/10: Lakeside and Bukit Batok moved from 3rd stage to LIVE!
16/08/10: Clementi and Bukit Gombak moved from 3rd Stage to LIVE!
14/08/10: Chinese Garden moved from 2nd stage to 3rd stage
03/08/10: Paya Lebar moved from 1st stage to 2nd stage
10/07/10: Eunos moved from 1st stage to 2nd stage
24/06/10 : Bukit Batok moved from 2nd stage to 3rd stage08/06/10: Lakeside moved from 2nd stage to 3rd stage
02/05/10: Kranji, Marsiling and Woodlands added on 1st stage
01/05/10: Bukit Gombak moved from 2nd stage to 3rd stage
14/04/10: Khatib added on 1st Stage
28/03/10: Clementi moved from 2nd Stage to 3rd Stage
21/03/10: Yew Tee added on 1st stage
15/03/10: Ang Mo Kio added on 1st stage
14/03/10: Yio Chu Kang added on 1st Stage
13/03/10: Kallang, Aljunied, Paya Lebar, Eunos, Bedok, Kembangan and Simei
added on 1st stage
04/03/10: Choa Chu Kang added on 1st stage
26/02/10: Tampines, Dover, Commonwelth, Queenstown, Buona Vista & Rehill
added on 1st stage
23/02/10: Pioneer & Tanah Merah added on 1st stage
12/02/10: Lakeside moved frm 1st stage to 2nd stage
09/02/10: Bukit Gombak moved from 1st stage to 2nd stage
06/02/10: Bukit Batok moved from 1st stage to 2nd stage
Joo Koon & Bukit Gombak added on 1st stage
31/01/10: Admiralty removed from 2nd stage
30/01/10: Chinese Garden moved from 1st stage to 2nd stage
Admiralty added on 2nd stage
Commonwealth spelt wrongly.. please edit. :)
ALJ EB &WB :27
PYL EB & WB: 25 (TBC). Forgot to check HHPSD near CCL link.
Eunos HHPSD is IN OPERATIONAL as of today
PYL EB & WB: 27